Khor Mor gas field attack halts output and cuts Kurdistan power: what we know
A drone attack on the Khor Mor gas field in Iraq's Kurdistan Region late on Sunday 8 November 2026 started a fire and halted gas production, removing about 2,800 megawatts of power generation, regional officials said. No group has claimed responsibility, and Iraq's prime minister has ordered a joint investigation.

Gas production at the Khor Mor field in Iraq's Kurdistan Region stopped late on Sunday 8 November 2026 after an attack set part of the facility on fire, regional officials said. The shutdown cut gas to power stations and removed about 2,800 megawatts (MW) of generating capacity from the region's grid, according to the Kurdistan Regional Government's electricity ministry. No casualties were reported in initial assessments, and no group has claimed responsibility.
Iraq's prime minister, Ali al-Zaidi, ordered a joint investigation with Kurdish authorities, his office said early on Monday, according to 964media.
What happened at Khor Mor?
The Kurdistan Regional Government's ministries of natural resources and electricity said in a joint statement that the field "came under a terrorist attack" at 11:00 pm local time (20:00 GMT), as quoted by AFP. A Kurdish security source told AFP that an "explosive-laden drone" hit the field, and two sources in the regional electricity ministry told Reuters that a single drone strike hit a liquefied petroleum gas (LPG) storage tank, causing a fire.
Accounts of exactly what was hit differ slightly. Kurdistan24's correspondent reported that the strike hit the facility's "Old Field" section, which handles daily LPG production, and said that section had not been targeted before. A source quoted by 964media said the attack hit the LPG loading section, which loads about 1,500 tonnes a day, while another described the target as a production section known as Ka1. A second 964media source said debris suggested a drone, but that it was not yet certain whether a drone or rocket was used.
An alarm sounded before the impact and workers moved to shelters, according to Kurdistan24 and 964media. Prime Minister al-Zaidi said the attack caused no casualties, based on an initial assessment, Reuters reported.
LPG is the bottled gas many households in Iraq use for cooking and heating. Khor Mor also supplies natural gas by pipeline to power stations.
How much electricity has been lost, and who is affected?
The regional electricity ministry gave a figure of about 2,800 MW, or 2.8 gigawatts, of lost generation, Reuters and 964media reported. 964media reported power cuts in parts of Erbil, Duhok and Zakho. Al Jazeera reported on Monday that more than 70% of the Kurdistan Region was without power; The Daily Context has not independently confirmed that figure.
Omed Ahmed, the electricity ministry spokesperson, told 964media the ministry was trying to avoid a full blackout. It would cut power first to places that need it least, with households affected only as a last resort. He said the ministry was turning to the Dukan and Darbandikhan hydropower dams and to plants that can run on other fuels, to keep hospitals, water stations and other critical sites supplied. He told Kurdistan24 that restoring normal supply would depend on gas production restarting at Khor Mor.
According to 964media, the regional ministries said in July, during an earlier shutdown, that household cooking-gas supplies would continue because the federal oil ministry had agreed to meet the region's daily demand. Officials have not said whether the same arrangement applies now.
Why is Khor Mor so important?
Khor Mor is in the Qadir Karam subdistrict of Chamchamal, in Sulaymaniyah governorate. It is run by the Pearl Petroleum consortium, led by the UAE-based companies Dana Gas and Crescent Petroleum. According to 964media, the field produces about 750 million cubic feet of natural gas a day, and its operators say it fuels more than 80% of the Kurdistan Region's electricity generation.
That dependence on one site is why attacks on it cause widespread power cuts. The attack came about a week after the scheduled end of the field's annual month-long maintenance, which 964media said was set for 2 October to 2 November.
Has Khor Mor been attacked before?
Yes, repeatedly. Shafaq News and 964media list several earlier attacks:
- Rockets landed near the field in June 2022.
- A drone attack in January 2024 temporarily halted production.
- A drone strike in April 2024 killed four foreign workers, reported as Yemeni nationals.
- A drone attack on 2 February 2025 caused no casualties or damage.
- On 26 November 2025, a strike set a storage tank on fire and cut about 2,600 MW of generation. Production restarted within days after an agreement between the regional government and Dana Gas.
According to 964media, a federal Iraqi investigation into the November 2025 attack found that two drones had been launched from east of Tuz Khurmatu in Salah al-Din governorate. It said that was the 11th attack on the field from the same area and that arrest warrants had been issued for several suspects.
Production has also been interrupted this year for security reasons. 964media reported that Dana Gas suspended output from 28 February until mid-April after the outbreak of the US-Israeli war with Iran, and halted it again in July, citing credible security threats.
Who is responsible?
No group has claimed the attack, and authorities have not said where it came from. Kurdistan24 reported that security officials had not disclosed the launch location or direction. The attack happened amid wider regional hostilities, including attacks on energy facilities elsewhere in the Gulf. Any link to those hostilities has not been established, so readers should treat speculation about responsibility with caution.
What happens next?
According to a 964media source at the field, crews will inspect the pipelines once the fire is out. If damage is limited, production could restart. If it is extensive, the field would stay offline until repairs are complete. Neither the operators nor the regional government had given a restart timetable as of early Monday.
In November 2025, gas began flowing to power stations again about three and a half days after the attack, according to The National, but the damage this time has not yet been assessed publicly. The joint federal and regional investigation ordered by al-Zaidi may also shed light on who carried out the attack. The Daily Context will update this article when officials or the operators report on damage, restart plans or responsibility.
Image: Photo: Osama Shukir Muhammed Amin FRCP(Glasg) / Wikimedia Commons, CC BY-SA 4.0 (https://commons.wikimedia.org/wiki/File:Dukan_Dam,_shooting_from_Lake_Dukan,_Sulaymaniyah,_Iraqi_Kurdistan,_showing_the_arch_dam.jpg) — April 2013 file photo of Dukan Dam, one of the hydropower plants officials said they would use; not of Khor Mor
About this article: prepared by The Daily Context editorial desk using automated, source-based reporting from the publications linked below. No reporter was on the ground.
Sources
- 964media: Khor Mor attack cuts nearly 3,000 MW as PM Zaidi orders joint probe (9 November 2026): https://en.964media.com/54956/
- Reuters via Al-Monitor: Production suspended at Iraq's Khor Mor gas field after drone attack, sources say (8 November 2026): https://www.al-monitor.com/originals/2026/11/production-suspended-iraqs-khor-mor-gas-field-after-drone-attack-sources-say
- AFP via Arab News: Attack on Iraq gas complex cuts supply, authorities say (8 November 2026): https://www.arabnews.com/middle-east/attack-on-iraq-gas-complex-cuts-supply-authorities-3010589
- Kurdistan24: Attack on Khor Mor gas field halts production, causes major fire (8 November 2026): https://www.kurdistan24.net/en/story/951677/khor-mor-gas-field-targeted-in-drone-attack
- Shafaq News: Drone targets Khor Mor gas field in Al-Sulaymaniyah (8 November 2026): https://api.shafaq.com/en/Kurdistan/Drone-targets-Khor-Mor-gas-field-in-Al-Sulaymaniyah
- Al Jazeera live: Iran war live, drone hits Iraq gasfield (9 November 2026): https://www.aljazeera.com/news/liveblog/2026/11/9/iran-war-live-trump-says-land-blockade-in-effect-drone-cuts-power-in-iraq
- The National: Operations resume at Iraq's Khor Mor gasfield after drone strike (30 November 2025): https://www.thenationalnews.com/news/mena/2025/11/30/operations-resume-at-iraqs-khor-mor-gasfield-after-drone-strike/
Kabeer Ahmad